Adelaide MotoGP Circuit Design Revealed: Nearly 400 Park Lands Trees Face Removal

South Australia has unveiled the design for Adelaide’s new MotoGP circuit, setting the stage for international motorcycle racing to return to the city’s eastern park lands from November 2027.
The proposed 4.13-kilometre, 15-turn circuit will run through the Adelaide Park Lands and is expected to cost approximately $96 million to deliver. The project is also intended to accommodate the Tour Down Under from January 2028, creating a major new sporting venue in the city.
However, the circuit design has sparked controversy over its environmental impact, with plans indicating that close to 400 trees could be removed, including 42 trees classified as significant.
Adelaide’s New MotoGP Circuit
The South Australian Government released the circuit design on Sunday, 30 August 2026, outlining the proposed layout and infrastructure for the new Adelaide MotoGP venue.
The 4.13km track will feature 15 turns and pass through the eastern section of Adelaide’s Park Lands. The venue is being developed with the aim of bringing MotoGP racing to Adelaide in November 2027.
The circuit will also form part of the infrastructure planned for the Tour Down Under, which is scheduled to use the venue from January 2028.
Government investment in the project is estimated at $96 million, making it one of the significant sporting infrastructure projects planned for Adelaide in the coming years.
Nearly 400 Trees Could Be Removed
The biggest point of contention surrounding the circuit is its impact on Adelaide’s Park Lands.
According to the released plans, close to 400 trees are expected to be removed to make way for the circuit and associated infrastructure. Among them are 42 trees classified as significant.
The scale of the proposed tree removal has prompted criticism from people concerned about the environmental and heritage value of the Adelaide Park Lands.
The issue has also raised questions about how the number of trees affected by the project was communicated to the public.
Transparency Row Over Earlier Tree Estimate
The proposed tree removal has become particularly contentious because of comments made by South Australian Premier Peter Malinauskas earlier this year.
In February 2026, Malinauskas said that approximately 45 trees would need to be removed for the project.
The newly released plans indicating that close to 400 trees could be affected have therefore prompted questions about the difference between the earlier figure and the current assessment.
The discrepancy has become a central part of the public debate, with questions being raised about how the project's environmental impact was calculated and communicated.
The Government will now face scrutiny during the public consultation process as residents, community groups and other stakeholders consider the proposed circuit.
Public Consultation Opens
Public consultation on the project began on 31 August 2026 and will remain open until 20 September 2026.
The consultation gives members of the public an opportunity to review the proposal and provide feedback before the project progresses further.
For Adelaide residents, the consultation is particularly significant because the circuit would occupy part of the city's historic Park Lands, an area valued for its open spaces, recreation, greenery and cultural significance.
Community feedback is expected to focus not only on the sporting and economic opportunities presented by MotoGP but also on the project's effects on trees, public space, traffic, accessibility and the broader character of the Park Lands.
Why Adelaide Is Hosting MotoGP
Bringing MotoGP to Adelaide is intended to strengthen South Australia’s position as an international sporting and tourism destination.
A major motorcycle racing event could attract visitors from interstate and overseas while generating additional activity for hotels, restaurants, retailers and other local businesses.
The Government is also positioning the circuit as a multi-purpose venue rather than a facility used exclusively for MotoGP.
With the Tour Down Under expected to use the circuit from January 2028, the project could become part of Adelaide's broader calendar of major sporting events.
Balancing Sport and the Park Lands
The central challenge for the project will be balancing the benefits of hosting major international sporting events with the environmental and community value of the Park Lands.
Adelaide's Park Lands are an important part of the city's identity. Any permanent or semi-permanent infrastructure within them is therefore likely to attract considerable public attention.
The proposed removal of almost 400 trees has intensified that discussion.
The Government will need to demonstrate how environmental impacts will be managed and whether replacement planting, landscaping or other measures can offset some of the effects of construction.
For supporters, the circuit represents an opportunity to bring another globally recognised sporting event to Adelaide. For opponents and concerned residents, the scale of tree removal raises questions about whether the benefits justify the impact on the Park Lands.
What Happens Next?
The immediate focus will be on the public consultation period, which runs from 31 August to 20 September 2026.
Feedback received during this period will help inform the next stages of the project.
With MotoGP planned for November 2027, there is a relatively tight timeframe for design development, approvals, construction and preparation of the venue.
The Tour Down Under's planned use of the circuit from January 2028 adds another deadline to the project schedule.
The coming months are therefore likely to be important in determining how the circuit design evolves and how concerns over tree removal and the use of the Park Lands are addressed.
Adelaide MotoGP Circuit at a Glance
Location: Adelaide's eastern Park Lands
Circuit length: 4.13 kilometres
Number of turns: 15
Estimated project cost: $96 million
MotoGP planned: November 2027
Tour Down Under planned: January 2028
Trees potentially removed: Close to 400
Significant trees affected: 42
Public consultation: 31 August–20 September 2026